Baku, January 14, AZERTAC

“In Greece, over 190 km of our right of way have been cleared, 116 km line pipes strung, approximately 89 km welded, 30 km back-filled and 6.5 km fully reinstated,” TAP Head of Communications Lisa Givert told AZERTAC.

TAP will transport natural gas from the giant Shah Deniz II field in Azerbaijan to Europe. The approximately 878 km long pipeline will connect with the Trans Anatolian Pipeline (TANAP) at the Turkish-Greek border at Kipoi, cross Greece and Albania and the Adriatic Sea, before reaching Southern Italy.

TAP's routing can facilitate gas supply to several South Eastern European countries, including Bulgaria, Albania, Bosnia and Herzegovina, Montenegro, Croatia and others. TAP's landfall in Italy provides multiple opportunities for further transport of Caspian natural gas to some of the largest European markets such as Germany, France, the UK, Switzerland and Austria.

TAP will promote the economic development and job creation along the pipeline route; it will be a major source of foreign direct investment. With first gas sales to Georgia and Turkey targeted for late 2018, first deliveries to Europe will follow approximately in early 2020.

TAP's shareholding is comprised of BP (20%), SOCAR (20%), Snam (20%), Fluxys (19%), Enagás (16%) and Axpo (5%).
AZERTAG.AZ :TAP Head of Communications: Approximately 89 km welded in Greece



Xəbərin orijinal ünvanı: http://azertag.az/en/xeber/TAP_Head_of_Communications_Approximately_89_km_welded_in_Greece-1026634

Şahid olduğunuz hadisələrin video və ya fotosunu çəkərək bizə göndərin:
0552252950 (Whatsapp)

BU KATEQORİYADAN DİGƏR XƏBƏRLƏR